The Electric Grid
The century-old machine everything now depends on: why demand is surging for the first time in decades, and why the wires can't keep up.
The grid is the largest machine ever built, and for the first time in a generation we are asking it to grow. After twenty flat years, electricity demand is surging while the machine that delivers it has a decade-long to-do list.
What this argues
- Demand growth is back+25% by 2030, the first real growth since the 1990s.
- The queue is the crisisAbout 2,060 GW of ready generation still can't get connected (down from a 2,600 GW peak).
- Hardware is scarceTransformers and turbines have multi-year waits.
- The fixes are knownReform, reconductoring, storage and flexible demand.
- Whoever solves power wins AIThe grid is now a strategic asset, not plumbing.
What has changed
Updated November 2026
US power demand is set for a second and third straight record
EIA's July 2026 Short-Term Energy Outlook (via Reuters, 7 July 2026) put US consumption at a record 4,195 billion kWh in 2025, rising to 4,269 billion kWh in 2026 and 4,399 billion kWh in 2027, led by data centres and electrification. Commercial demand is expected to exceed residential demand in 2026 for the first time on record. An earlier EIA outlook (February 2026) put baseline load growth at 1.9% in 2026 and 2.5% in 2027.
The interconnection queue shrank, but only from a record
- LBNL's Queued Up 2026 edition (June 2026) counted over 2,060 GW of generation and storage seeking connection at the end of 2025, a 10% fall from a year earlier.
- High withdrawals and fewer new requests drove the fall; the third and fourth quarters of 2025 saw record withdrawal volumes (Interconnection.fyi, citing LBNL data).
- Median time from request to signed interconnection agreement was 45 months in 2025, and from agreement to operation 31 months, up from 21 in 2008 (LBNL, June 2026).
FERC moved from a proposal to show cause orders on large loads
After DOE asked FERC in October 2025 to standardise large-load (20 MW and up) interconnection, FERC on 18 June 2026 issued show cause orders to CAISO, ISO New England, MISO, NYISO, PJM and SPP, finding their rules appeared inadequate (Utility Dive, 2026). The orders cover study processes, cost shifts, co-location, flexible loads and alternative transmission technologies such as advanced conductors. FERC extended the response deadline to mid-November 2026 (Utility Dive, August 2026). States keep authority over retail sales and siting.
Transformer waits remain above two years, with new factories coming
Wood Mackenzie's Q2 2025 survey, as reported by POWER Magazine in 2026, put average lead times at about 128 weeks for power transformers and 144 weeks for generator step-up units, with a roughly 30% supply deficit for power transformers in 2025. Announced North American factory investment reached nearly $1.8 billion by September 2025, including Hitachi Energy's $457 million Virginia plant (targeted for 2028) and Siemens Energy's $150 million North Carolina plant (production expected early 2027). Press reports in 2026 cite GSU waits above 160 weeks, but those come from secondary sources.
Not refreshed: data centre share of US electricity (2026-2030 estimates), utility capex (about $180B a year), the $2T+ grid investment estimate, the 2026 transformer lead-time survey, the ICF 2030 demand forecast, and asset-age and miles-of-line figures; no newer primary source was read for these.
What the Grid Is
The machine, briefly
A century of building, then a long pause
- Pearl Street: Edison lights lower Manhattan
- Rural power: the New Deal wires America
- Northeast blackout: interconnection's growing pains
- Deregulation: markets replace monopoly in half the US
- The strain: new demand meets old iron
From turbine to toaster, in four steps
- Generate: plants and farms make power at scale.
- Transmit: high-voltage lines move it across states.
- Distribute: local wires step it down to neighbourhoods.
- Balance: operators match supply to demand every second.
Power steps down all the way to your wall
- ~20 kV at the plant (the power plant)
- 230-765 kV highways
- stepped to ~13 kV
- the local feeders
- 120/240 V (your outlet)
The grid is evolving from one-way to many-way
| Yesterday: hub and spoke | Tomorrow: mesh | |
|---|---|---|
| Flow | big plants push power outward | solar, batteries and EVs flow both ways |
America's grid, by the numbers
The grid was largely built in two bursts, the 1960s-70s and the 1990s. The bill for that aging arrives at exactly the moment demand growth returns.
The Demand Shock
Growth returns after 20 flat years
US demand was flat for two decades, now it's climbing
View the data
| US | |
|---|---|
| 2005 | 3800 |
| 2010 | 3850 |
| 2015 | 3900 |
| 2020 | 3850 |
| 2023 | 4050 |
| 2026 | 4270 |
| 2030 | 5000 |
Source: EIA history; EIA STEO Jul 2026 (2026 forecast); ICF forecast (2025) for 2030 · values read from the chart, approximate
The chart marks two flat decades, then +25% by 2030. Values are read approximately from the axis; the 2026 point is EIA's July 2026 forecast of 4,269 billion kWh (2025 was a record 4,195 billion kWh).
Data centres alone could take ~12% of US power by 2030
View the data
| US | |
|---|---|
| 2023 | 4.4 |
| 2026e | 7 |
| 2028e | 9.5 |
| 2030e | 12 |
Source: LBNL; EPRI (2024-25)
It isn't only AI
| Source of demand | What it adds |
|---|---|
| Data centres & AI | the loudest and lumpiest new load |
| EVs | every ten million EVs = another 1-2% of demand |
| Heat pumps | electrifying heating shifts winter peaks |
| Reshored factories | chips, batteries and steel are power-hungry |
| Hydrogen & fuels | electrolysis, if it scales, is enormous |
| Air conditioning | a warming world runs the compressor harder |
What one AI campus asks of the grid
For twenty years the grid's problem was too little growth. Overnight, the problem became too much. An industry staffed, financed and regulated for stagnation is being asked to sprint.
The Bottlenecks
Where it all jams
2,000+ GW of projects are still waiting to connect
View the data
| US | |
|---|---|
| 2015 | 300 |
| 2018 | 600 |
| 2021 | 1400 |
| 2023 | 2000 |
| 2025 | 2600 |
| End-2025 | 2060 |
Source: LBNL interconnection data (2025); LBNL Queued Up 2026 edition (Jun 2026) · values read from the chart, approximate
Transformer lead times quintupled
View the data
| US | |
|---|---|
| 2019 | 25 |
| 2021 | 50 |
| 2023 | 100 |
| 2025 | 128 |
Source: Wood Mackenzie; industry surveys (2025)
Each layer adds years
| Layer | Delay |
|---|---|
| Hardware | transformers 2-3 yrs; turbines similar |
| Interconnection | ~45 months median from request to signed agreement (LBNL, 2026) |
| Permitting | lines can take 10-15 years end to end |
| Politics | every mile crosses someone's backyard |
Against data centres that want power in two years and factories in three. The mismatch between demand's clock and the grid's clock is the single most important number in American energy.
The mechanics of interconnection gridlock
| Mechanism | What happens |
|---|---|
| Study cascades | each project's study depends on every other project's fate |
| Speculative entries | developers file placeholders; most never get built |
| Serial processing | one-at-a-time reviews from a first-come era |
| Cost-allocation fights | who pays for upgrades stalls everything |
| Staff shortages | too few engineers to run the studies |
| Withdrawal chains | one dropout forces everyone's restudy |
The Money
The build-out bill
What fixing and growing the grid costs
The grid build-out's winners and payers
| The winners | The payers | |
|---|---|---|
| 1 | Equipment makers: transformers, cables, switchgear | Ratepayers: bills fund the build-out |
| 2 | Utilities: bigger rate base, regulated returns | Big load: data centres pay to jump queues |
| 3 | Grid tech: software squeezing more from wires | Taxpayers: subsidies and guarantees |
| 4 | Storage: batteries as grid infrastructure | Late arrivals: projects priced out by delay |
Transmission, distribution, transformers and storage: the third great electrification build. For scale: that approaches the inflation-adjusted cost of the entire Interstate Highway System, twice.
The utility doom loop, the risk regulators fear
- Bills rise
- Rich customers defect to solar
- Fewer payers left
- Fixed costs concentrate
- Bills rise faster (the loop repeats: the death spiral)
Electricity used to be boring infrastructure. It is now the binding constraint on the two biggest builds of the era, AI and the energy transition. That promotion, from plumbing to strategic asset, is the grid's whole story this decade.
The Fixes
Known, proven, and slow
Six ways to unjam the grid
| Fix | What it does |
|---|---|
| Queue reform | first-ready-first-served instead of first-come |
| Reconductoring | advanced wires double capacity on existing towers |
| Grid-enhancing tech | sensors and software unlock hidden headroom |
| Storage as wires | batteries defer new lines by shaving peaks |
| Flexible demand | data centres and EVs that bend around scarcity |
| Behind-the-meter | generation built where the load is, skipping queues |
How a battery substitutes for a transmission line
- Find the pinch: a corridor that congests a few hundred hours a year.
- Site batteries: at each end of the constrained line.
- Shift the peak: charge off-peak, discharge through congestion.
- Defer the build: the $1B line waits a decade, or forever.
Regulated states versus market states
| Regulated (the South, West) | Markets (Texas, PJM, etc.) | |
|---|---|---|
| Model | one utility owns it all | competition sets prices |
| Build | faster, one decider | price signals drive it |
| Risk | ratepayers hold it | investors hold it |
| AI deals | bilateral, behind closed doors | priced in the open |
What the next five years actually look like
- Big load routes around. AI campuses co-locate with plants or build their own power.
- Batteries flood in. Storage is the fastest-permitted asset on the grid.
- Reconductoring spreads. The quiet doubling of existing corridors.
- Reform grinds forward. FERC and states inch queues toward sanity.
Risks & Politics
The honest chapter
Build-out boom or ratepayer revolt?
| The boom case | The revolt case | |
|---|---|---|
| 1 | Demand is real. AI and factories are signed contracts | Bills rise. Ratepayers fund data-centre growth |
| 2 | Capital is ready. Utilities and funds want to build | Siting fights. Every line breeds lawsuits |
| 3 | Tech headroom. Cheap fixes still unexploited | Political whiplash. Policy reverses by administration |
| 4 | Bipartisan need. Reliability polls well everywhere | Forecast risk. Overbuild if AI demand disappoints |
Six risks a serious observer tracks
| Risk | Description |
|---|---|
| Reliability | extreme weather against an aging fleet |
| Cyber & physical | the grid is the top-tier infrastructure target |
| Cost overruns | megaprojects rarely land on budget |
| Demand whiplash | AI slowdown stranding new capacity |
| Workforce | linemen and engineers retiring faster than hiring |
| Fragmentation | 3,000 utilities, no single pilot at the wheel |
Resilience looks expensive until you price its absence.
What to Watch
Signposts, not predictions
Four dials worth watching
Five signposts for the next 24 months
- Do queues start shrinking? Reform's first measurable win.
- Do transformer waits peak? New factories vs surging demand.
- Does big load go behind-the-meter? The workaround becoming the norm.
- Does a state pioneer AI tariffs? The template others will copy.
- Does a major outage reset politics? One bad week changes everything.
Reference
Glossary & sources
Plain-language glossary
| Term | Meaning |
|---|---|
| Transmission | high-voltage highways moving power long distances |
| Distribution | local streets delivering power to buildings |
| Interconnection queue | the waiting list to plug into the grid |
| Transformer | the device that steps voltage up or down |
| Peak demand | the single highest moment of consumption |
| Reconductoring | restringing old towers with higher-capacity wire |
| Behind-the-meter | power made and used on-site, skipping the grid |
| Rate base | the assets a utility earns regulated returns on |
The 20th century's grid was built for a nation of consumers. The 21st century's must serve a nation of computers, factories and batteries, all at once. Same wires, new civilisation. That is the engineering brief of the next two decades.
Every technology of the decade (the model, the robot, the EV, the factory) ends its supply chain at the same place: a transformer that takes three years to arrive. The grid is where the future queues.
The five conclusions to take away
- Demand growth is structural: five megatrends, one set of wires.
- Process, not physics, is the constraint: queues and permits set the pace.
- Hardware scarcity is real: transformers are the new GPUs.
- The money flows to the build: utilities and equipment makers feast.
- Power is strategy now: energy access decides where the future gets built.
Sources & Further Reading
- LBNL: 'Queued Up' interconnection data; data-centre demand study (2024-25).
- Wood Mackenzie: transformer supply-deficit analysis (2025).
- EPRI: data-centre load forecasts to 2030.
- ICF: US electricity demand growth outlook (2025).
- DOE: National Transmission Needs Study; grid reports.
- S&P Global: data-centre power demand tracking (2025).
- Utility filings: capital plans and rate cases (2025-26).
- Figures marked 'estimate' are compilations.
Sources cited
ICF · LBNL · Wood Mackenzie · EPRI · EIA · DOE · S&P Global · Industry data and disclosures · Utility filings · EIA STEO, Jul 2026 (via Reuters) · LBNL Queued Up 2026 edition, Jun 2026 · Interconnection.fyi, 2026 · Utility Dive, 2026 (FERC show cause orders) · POWER Magazine, 2026 (Wood Mackenzie transformer data) · pv magazine USA, May 2026
Keep reading
Research, not investment advice. Figures as of , from the sources cited.
Legal information and disclosures
These are my own views as of the update shown on this page. They can change without notice, and I have no duty to update them. Past performance does not indicate future results, and any investment can lose money.
This is for education only. It is not investment, legal, tax, medical or accounting advice, and it is not an offer to sell or a solicitation to buy any security in any jurisdiction. It does not consider your goals or circumstances.
Figures from company filings, public agencies and other third parties are believed to be reliable, but I have not independently verified them and cannot guarantee them. Forecasts and anything marked as an estimate rest on assumptions that may prove wrong.
Please do not copy or republish this material without my written consent.